Some of you may have been following the saga of our server room refurbishment. The main part of the refurbishment has been done for a while and we even took pictures of the process, but we haven’t posted them until now.
So here’s what it looked like while we were putting the new networking in. We installed patch panels in each server rack so we only have to run a short network lead from each server to the nearest network socket. Originally we used to have network cables running around the room on a ceiling tray and back to a single large patch panel. It was difficult to tell what was plugged in where. The new system is a great improvement, although you might not think so from the photo below of it going in. It took a lot of effort not to lose track of which cable was which.
Each of the grey cables has eight wires inside which have to be connected to the correct terminals on the new patch panels with a punchdown tool. That was several thousand wires to connect! In total we used over a kilometre of the grey ethernet cable.
It all took a long time but means that the cabling is now much tidier and we’re very unlikely to pull out the wrong lead.
-
Recent Posts
-
Recent Comments
-
Archives
- August 2021
- April 2021
- March 2021
- July 2020
- May 2020
- March 2020
- February 2020
- January 2020
- November 2019
- June 2019
- May 2019
- April 2019
- March 2019
- July 2018
- June 2017
- October 2016
- September 2016
- August 2016
- June 2016
- April 2016
- March 2016
- February 2016
- November 2015
- October 2015
- September 2015
- August 2015
- June 2015
- April 2015
- March 2015
- January 2015
- October 2014
- September 2014
- August 2014
- July 2014
- January 2014
- September 2013
- July 2013
- May 2013
- February 2013
- January 2013
- December 2012
- November 2012
- October 2012
-
Categories
-
Meta