We’re doing a complete refurbishment of the Unilever server room this summer. The original plan was to move all the servers out by the end of July in order for work to start in August. The room holds three compute clusters and half the servers that provide the Chemistry IT infrastructure, so we’d planned to do this gradually over a period of weeks.
Unfortunately the ageing air conditioning in the room didn’t quite make it to August. It failed last Sunday. Luckily it’s been possible to bring all the refurb work forward by three weeks. So in the last few days we’ve gone from this
to this
to this.
That last server sitting on the trolley has to be moved out of working hours, and will be gone by Monday. The rack to the left is the only thing that will remain in the room, and that’s because it’s supplying all the phones and networking to the Unilever centre.
The servers that came out of the Unilever room have been spread around the department. We’ve moved some less important machines out of the other server rooms to make space for them. Some of the displaced machines have been switched off for the duration (if that affects you then you will have had an email from us) and quite a few others have found a temporary home in a lab that’s awaiting a refurb.
Now all we have to do is move them all back in a month’s time.
-
Recent Posts
-
Recent Comments
-
Archives
- August 2021
- April 2021
- March 2021
- July 2020
- May 2020
- March 2020
- February 2020
- January 2020
- November 2019
- June 2019
- May 2019
- April 2019
- March 2019
- July 2018
- June 2017
- October 2016
- September 2016
- August 2016
- June 2016
- April 2016
- March 2016
- February 2016
- November 2015
- October 2015
- September 2015
- August 2015
- June 2015
- April 2015
- March 2015
- January 2015
- October 2014
- September 2014
- August 2014
- July 2014
- January 2014
- September 2013
- July 2013
- May 2013
- February 2013
- January 2013
- December 2012
- November 2012
- October 2012
-
Categories
-
Meta